CBBT Tunnel Construction Continues; Expected Completion Pushed to 2024

0
2511
The image above shows “Chessie,” the tunnel boring machine manufactured in Germany, which will be used during construction of the parallel Thimble Shoals tunnel of the Chesapeake Bay Bridge-Tunnel. Photo courtesy of the CBBT.

By Stefanie Jackson – Construction continues on the Chesapeake Bay Bridge-Tunnel’s first parallel tunnel, near the Virginia Beach side of the bridge, with projected completion in 2024, approximately two years later than originally estimated.

“The key emphasis for the collective project team is high quality and durability over speed for completion deadlines,” said Chesapeake Bay Bridge-Tunnel Executive Director Jeff Holland.

The team consists of two groups: the Chesapeake Bay Bridge-Tunnel project management team and the Chesapeake Tunnel Joint Venture, three contractors designing and building the tunnel: Dragados USA, Schiavone Construction Company LLC, and the Mott MacDonald Group.

The goal is for the new tunnel to “have a long-term durability of over 100 years,” better than the original tunnels, which have required several improvements, Holland said.

Those are the Thimble Shoals tunnel, near Virginia Beach, and the Chesapeake Channel tunnel, near Northampton County.

The delay in construction of the new Thimble Shoals tunnel was caused by a combination of three factors: the permitting process, the termination of a key subcontractor, and the design of the marine-works portion of the project, Holland said.

But new tunnel construction isn’t the only improvement that’s been going on at the Chesapeake Bay facility. A $1.6 million project was recently completed, which replaced the lights in both existing tunnels with new LED lights.

The LED lighting was installed to enhance safety in the tunnels and save electricity. LED lighting also will be used in the new tunnel.

The majority of the Chesapeake Bay Bridge-Tunnel’s electric consumption in 2018, or 45%, lighted its tunnels.

Of the remaining electricity the facility used that year, 24% ventilated the tunnels, 15% lighted roadways, and 16% provided all other electricity demands.

The tunnel lights used nearly 3.6 million kilowatts of power out of about 7.9 million kilowatts used by the Chesapeake Bay Bridge-Tunnel in 2018.

The parallel tunnel at Thimble Shoals is being built to alleviate traffic congestion near Virginia Beach during the busy summer tourist season when more people are traveling. The additional tunnel also can serve as a backup in case of an emergency.

A groundbreaking ceremony was held in September 2017 on One Island, one of four manmade islands spanned by the Chespeake Bay Bridge-Tunnel.

A restaurant and gift shop on One Island were closed permanently to save money on the $756 million project. Rebuilding the restaurant, gift shop, parking lot, and entrance and exit ramps would have pushed the project cost to more than $1 billion.

The tunnel will be dug by a 325-foot-long, cylinder-shaped boring machine nicknamed “Chessie,” after a long-necked monster that, according to legend, lives in the Chesapeake Bay, like “Nessie,” the mythical Loch Ness monster of Scotland.

“Chessie” was the winning entry in a naming contest held in elementary and middle schools on both sides of the bridge-tunnel in 2018. The winning entry was submitted by Grace Bentley, of Nandua Middle School.

Chessie was manufactured by a German company, Herrenknecht, to bore the one-mile-long, 42-foot-wide tunnel, which will be 70 feet underground, or 15 feet deeper than the existing Thimble Shoals tunnel.

Not only will the parallel tunnel be buried deeper than its counterpart, this will be the first time the boring technique will be used at the Chesapeake Bay facility. The two existing tunnels were built with the immersed tube method. The tunnels were prefabricated in sections that were floated out into the Chesapeake Bay and sunk into U-shaped trenches.

The boring technique was chosen for the parallel tunnel to limit the amount of work to be done while exposed to wind and waves and to avoid impact to the existing tunnel.

The boring machine’s launching pit will be located at One Island. The launching pit will eventually become the southbound exit of the new tunnel.

At the launching pit, a secant pile wall (a retaining wall of interlocking drilled piles) will ensure a watertight excavation. The excavation area will be braced, with a concrete cradle at the bottom to hold the boring machine, which will be lowered one section at a time by a lift tower.

A temporary dock at One Island will be used for mucking and transferring excavation disposal, allowing barges to bring pieces of tunnel onsite, and storing sections of the tunnel liner.

On the front of the boring machine is a cutting wheel that turns and breaks up the soil that is transferred to the rear on a conveyor belt.

Pressure from hydraulic cylinders keeps the cutting wheel pressed against the face of the soil and prevents uncontrolled penetration of soil and water.

The completed tunnel will consist of rows of tunnel rings, with each ring made of 10 tunnel liner segments – nine large segments and one small segment called the key. The tunnel liner segments are manufactured by Concrete Systems Inc., of Chesapeake, and will be transferred into the work area by mine cars.

Each segment is positioned precisely and bolted next to the previous ring. The remaining gap between the soil and the liner ring is continuously filled with grout, creating a seal between the interior work area and the exterior soil and water.

Chessie is expected to arrive at the Chesapeake Bay Bridge-Tunnel in late 2021.

The Chesapeake Bay Bridge-Tunnel’s parallel tunnel project will be funded 29% by general funds, 34% by state and federal loans, and 37% by toll revenue bonds.

To pay for the project, tolls are expected to increase 10% every five years. The toll rate schedule was last updated Jan. 1, 2019. A round trip by car, if the return trip is made within 24 hours, currently costs $20.

Without EZ Pass, each trip is $14 to $18, depending on the time of travel. See the full toll schedule at www.cbbt.com

Previous articleGardner Dangerous Structure 12.25, 1.1
Next articleDominion Files Plan for Offshore Wind, Triggering Federal Review Process